DISCLAIMER: TRADITION LIEN SERVICE, a Division of Tradition Software, Inc. makes no warrant, express or implied for the use of this website. In no event shall TRADITION LIEN SERVICE be liable to anyone for any problem, claim or loss arising out of the use of TraditionLienService.com. TRADITION LIEN SERVICE is not engaged in practicing law nor does Tradition Software, Inc. provide legal advice in the state of West Virginia.
WEST VIRGINIA CODE
CHAPTER 38 LIENS

ARTICLE 2 MECHANICS’ LIENS

38-2-1 Contractor Has a Lien

38-2-2 Subcontractor Has a Lien

38-2-3 Lien for Materials and Equipment

38-2-4 Lien for Materials or Equipment

38-2-5 Lien of Worker

38-2-6 Lien of Worker

38-2-6a Lien of Architect, Engineer

38-2-7 Discharge of Lien, Perfection of Lien

38-2-8 Notice of Claim, Recording

38-2-9 Notice of Claim, Subcontractor, Recording

38-2-10 Notice of Lien, Material and Equipment Supplier

38-2-11 Notice of Lien, Supplies Furnished to Contractor or Subcontractor

38-2-12 Notice of Lien, Laborer

38-2-13 Notice of Lien, Laborer for Contractor or Subcontractor

38-2-14 Discharge of Lien, Failure to Give Notice

38-2-15 Service by Publication

38-2-16 One Contract

38-2-17 Priorities

38-2-18 Priority Among Lien Claimants

38-2-19 Demand for Itemized Account

38-2-20 Notice to Owner

38-2-21 Effect of Payments by Owner

38-2-22 Contracts to be Recorded with Bond, Effect

38-2-23 Failure to Record Contract and Bond, Effect

38-2-24 Bond Form

38-2-25 Property Outside City

38-2-26 Parties

38-2-27 Recordings

38-2-28 Proof of Sale, Effect

38-2-29 Multiple Improvements

38-2-30 Prevention of Performance

38-2-31 Lien of Worker Against Property of Corporation, Limitations

38-2-32 Discharge of Lien Against Corporation, Notice of Lien

38-2-33 Recording

38-2-34 Actions, Limitations, Intervention

38-2-35 Sale, Personal Judgment

38-2-36 Discharge of Lien, Deposit in Court, Hearing, Release, Escrow, Action, Receiver

38-2-37 Order of Discharge, Costs

38-2-38 Executor, Administrator, Assignee

38-2-39 Public Projects, Payment Bond, No Lien

ARTICLE 12 RELEASE AND ASSIGNMENT OF LIENS

38-12-1 Satisfaction, Release

38-12-2 Release by Trustee

38-12-3 Release by Trustee, Publication of Notice

38-12-4 Form of Release

38-12-5 Partial Release

38-12-6 Release by Assignor, Liability

38-12-7 Personal Representative

38-12-8 Recording

38-12-9 Recording, Indexing

38-12-10 Action for Failure to Release

38-12-11 Discharge or Impairment

38-12-12 Satisfaction, Entry

38-12-13 Liability of Clerk

WEST VIRGINIA CODE

CHAPTER 38 LIENS

ARTICLE 2 MECHANICS’ LIENS

38-2-1 Contractor Has a Lien

Every person, firm or corporation who erects, builds, constructs, alters, removes or repairs any building or other structure, or other improvement appurtenant to any such building or other structure, or who alters or improves the real property whereon the same stands, or to which it may have been removed, or who provides services for any of the foregoing, under and by virtue of a contract with the owner for such erection, building, construction, alteration, removal or repair, either for an agreed lump sum or upon any other basis of settlement and payment, shall have a lien upon such building or other structure or improvement appurtenant thereto, and upon the interest of the owner thereof in the real property whereon the same stands, or to which it may have been removed, to secure the payment of such contract price or other compensation therefore.

38-2-2 Subcontractor Has a Lien

Every person, firm or corporation who, under and by virtue of a contract with such general contractor as is mentioned in section one [s 38-2-1] of this article, or with a subcontractor for a part of such work, either for an agreed contract price or by day or by piece, or other basis of payment, shall furnish any part of the materials, machinery or other necessary supplies or equipment, or shall perform any labor, do any work or provide any services necessary to the completion of any general contract, such as is mentioned in section one of this article, shall have such a lien for his or her compensation, as is provided for in section one of this article.

8-2-3 Lien for Materials and Equipment

Every person, firm or corporation which shall furnish to any owner, for use in the erection, construction, alteration, repair or removal of any building or other structure or improvement appurtenant thereto, any materials, machinery or other equipment or supplies necessary to the completion of such building or other structure or improvement, shall have such a lien for his compensation as is mentioned in section one [s 38-2-1] of this article.

38-2-4 Lien for Materials or Equipment

Every person, firm or corporation, which shall furnish to any general contractor or to any subcontractor mentioned in sections one and two [ss 38-2-1, 38-2-2] of this article, any materials, machinery or other equipment or supplies necessary to the completion of any building or other structure mentioned in this article, or improvement appurtenant thereto, for use in the erection, construction, repair or removal thereof, by virtue of a contract between such general contractor or subcontractor and the materialman or furnisher of machinery, or other supplies or equipment necessary to the completion of such general contract, shall have such a lien for his compensation as is mentioned in section one of this article.

38-2-5 Lien of Worker

Every workman, artisan, mechanic, laborer or other person who performs any work or labor or provides any service in the erection, construction, repair or removal of any building or other structure or improvement appurtenant thereto, or who alters or improves the real property whereon the same stands, or to which it may have been removed, by virtue of a contract for such work and labor directly with the owner thereof, shall have such a lien for his or her compensation as is mentioned in section one [s 38-2-1] of this article.

38-2-6 Lien of Worker

Every workman, artisan, mechanic, laborer or other person who performs any work or labor or provides any service under the employment of any general contractor or of any subcontractor in the erection, construction, repair or removal of any building or other structure, or improvement appurtenant there to, or who alters or improves the real property whereon the same stands, or to which it may have been removed, necessary to the completion of such general contract, shall have such a lien for his or her compensation as is mentioned in section one [s 38-2-1] of this article.

38-2-6a Lien of Architect, Engineer

An architect, surveyor, engineer or landscape architect shall have a lien for his or her compensation as provided for in sections one through six [ss 38-2-1 through 38-2-6], inclusive, of this article for all materials furnished and all work done, or all services provided by such architect, surveyor, engineer and landscape architect as a contractor, subcontractor, materialman, mechanic or laborer, as the case may be. The lien shall be perfected and preserved in accordance with, and shall otherwise be subject to, the provisions of this article governing liens for contractors, subcontractors, materialmen, mechanics or laborers, as the case may be.

38-2-7 Discharge of Lien, Perfection of Lien

But the lien created and authorized by section one [s 38-2-1] of this article shall be discharged from and after one hundred (100) days from the completion of the contract, and the lien created and authorized by section two [s 38-2-2] of this article shall be discharged from and after seventy-five days from the completion of the subcontract, and the lien created and authorized by section three [s 38-2-3] of this article shall be discharged from and after one hundred (100) days from the furnishing of the last of the materials, machinery or other supplies and equipment, and the lien created and authorized by section four [s 38-2-4] of this article shall be discharged from and after seventy-five days from the date of the furnishing of the last of the materials, machinery or other equipment or supplies, and the lien created and authorized by section five [s 38-2-5] of this article shall be discharged from and after one hundred (100) days from the date of the performing of the last of the work and labor, and the lien created and authorized by section six [s 38-2-6] of this article shall be discharged from and after seventy-five days from the date of the performing of the last of the work and labor, unless within the respective periods, the claimant of any such lien shall have perfected and preserved the same, as hereinafter provided in this article.

38-2-8 Notice of Claim, Recording

For the purpose of perfecting and preserving his lien, any such general contractor as is mentioned in section one [s 38-2-1] of this article shall, within one hundred (100) days after the completion of his work provided for in such contract, cause to be recorded, in the office of the clerk of the county court [county commission] of the county wherein such property is situate, a notice of such lien, which notice shall be sufficient if in form and effect as follows:

Notice of Mechanic’s Lien

To ___________________

Notice is hereby given, in accordance with the laws of the State of West Virginia, that the undersigned claims a lien to secure the payment of the sum of $ _______ upon your interest in and to lot number ___________ of block number ________ as shown on the official map of the city of _____________ (or other adequate and ascertainable description of the real estate to be charged), and upon the following buildings, structures and improvements thereon: (List the buildings, structures or improvements sought to be charged.)

Given under my hand this ________ day of ______, 20___

State of West Virginia

County of _______________

________________________, being first duly sworn, upon his oath says that the statements contained in the foregoing notice of lien are true, as he verily believes. Taken, subscribed and sworn to before me this ____ day of ____, 19__

My commission expires ______________________________

(Official Capacity)

38-2-9 Notice of Claim, Subcontractor, Recording

For the purpose of perfecting and preserving his or her lien, every subcontractor mentioned in section two [s 38-2-2] of this article shall, within one hundred (100) days after the completion of his or her subcontract, give to the owner or his or her authorized agent, by any of the methods provided by law for the service of a legal notice or summons, a notice of lien, which notice shall be sufficient if in form and effect as
follows:

Notice of Mechanic’s Lien

To ________________

You will please take notice that the undersigned _________________ was and is subcontractor with ___________ who was and is general contractor for the furnishing of materials and doing of the work and labor, necessary to the completion of (here describe the nature of the subcontract) on that certain building (or other structure or improvement as the case may be), owned by you and situate on lot number _________ of block number _________ as shown on the official map of _________ (or other definite and ascertainable description of the real estate) and that the contract price and value of said work and materials is $_______ You are further notified that the undersigned has not been paid therefore (or has been paid only $_______ thereof) and that he claims and will claim a lien upon your interest in the said lot (or tract) of land and upon the buildings, structures and improvements thereon to secure the payment of the said sum.

__________________

State of West Virginia,

County of__________

__________________, being first duly sworn, upon his oath says that the statements in the foregoing notice of mechanic’s lien are true, as he verily believes.

Taken, subscribed and sworn to before me this _________ day of ______, 20__

My commission expires ____________

___________________

(Official Capacity)

But the lien shall be discharged and avoided, unless within one hundred (100) days after the completion of his or her subcontract as aforesaid the subcontractor shall cause to be recorded in the office of the clerk of the county commission of the county wherein the property is situate a notice of the lien, which notice shall be sufficient if in form and effect as that provided in section eight [s 38-2-8] of this article.

38-2-10 Notice of Lien, Material and Equipment Supplier

For the purpose of perfecting and preserving his lien, every materialman or furnisher of machinery or other necessary equipment, under a contract with the owner, as mentioned in section three [s 38-2-3] of this article, shall cause to be recorded in the office of the clerk of the county court [county commission] of the county wherein such property is situate, within one hundred (100) days from the date when he shall have ceased to furnish material or machinery or other necessary equipment, a notice of such lien, which notice shall be sufficient if in form and effect as that provided in section eight [s 38-2-8] of this article.

38-2-11 Notice of Lien, Supplies Furnished to Contractor or Subcontractor

For the purpose of perfecting and preserving his or her lien, every materialman or furnisher of machinery or other necessary equipment, who shall have furnished material, machinery or equipment under a contract with any contractor or with any subcontractor, as set forth in section four [s 38-2-4] of this article, within seventy-five days after he or she shall have ceased to furnish such material or machinery or other equipment, shall give to the owner, or his or her authorized agent, by any of the methods provided by law for the service of a legal notice or summons, a notice of such lien, which notice shall be suffieient if in form and effedt as follows:

Notice of Mechanic’s Lien.

To ___________________

You will please take notice that the undersigned ___________________ has furnished and delivered to _________ who was contractor with you (or subcontractor with ______________, who was contractor with you, as the case may be) for use in the erection and construction (or repair, removal, improvement, as the case may be) of (here list the buildings or other structure or improvement to be charged) on the real estate known as (here insert an adequate and ascertainable description of the real estate to be charged) and the said materials were of the nature and were furnished on the dates and in the quantities and at the price as shown in the following account thereof:

(Here insert itemized account.)

You are further notified that the undersigned has not been paid the sum of $______ (or that there is still due and owing to the undersigned thereon the sum of $_______) and that he claims a lien upon your interest in the said lot (or tract) of land and upon the buildings, structures and improvements thereon, to secure the payment of the said sum.

__________________

State of West Virginia,

County of __________

___________________, being first duly sworn, upon his oath says that the statements in the foregoing notice of lien contained are true, as he verily believes.

Taken, subscribed and sworn to before me this ________ day of _____, 20__

My commission expires _______________

____________________

(Official Capacity)

But the lien shall be discharged and avoided, unless, within one hundred (100) days after such materialman or other furnisher of machinery or other necessary equipment shall have ceased to furnish such materials or machinery or other equipment, he or she shall cause to be recorded in the office of the clerk of the county commission of the county wherein such property is situate a notice of such lien, which notice shall be sufficient if in form and effect as that provided in section eight [s 38-2-8] of this article, and which recorded notice need not include such itemized account.

38-2-12 Notice of Lien, Laborer

For the purpose of perfecting and preserving his lien every such workman, artisan, mechanic, laborer or other person as is mentioned in section five [s 38-2-5] of this article who shall have done any work or performed any labor upon any such building or improvement, under a contract with the owner thereof, shall cause to be recorded in the office of the clerk of the county court [county commission] of the county wherein such property is situate, within one hundred (100) days after he shall have ceased to perform any such work or labor, a notice of his lien, which notice shall be sufficient if in form and effect as that provided in section eight [s 38-2-8] of this article.

38-2-13 Notice of Lien, Laborer for Contractor or Subcontractor

For the purpose of perfecting and preserving his or her lien, every workman, artisan, mechanic, laborer or other person who shall have performed any work or labor upon the building or improvement thereto, under a contract with any general contractor or with any subcontractor, as set forth in section six [s 38-2-6] of this article, shall cause to be given to the owner, or his or her authorized agent, by any of the methods provided by law for the service of a legal notice or summons, within seventy-five days after he or she shall have ceased to perform any such work or labor, a notice of the lien, which notice shall be sufficient, if in form and effect as follows:

Notice of Mechanic’s Lien

To ___________________

You will please take notice that the undersigned has performed work and labor under a contract with _______. who was general contractor with you (or who was subcontractor with ______, who was general contractor with you) in the erection and construction (or removal, repair, improvement or otherwise, as the case may be) of a certain building (or other structure or improvement) on real estate known as (here insert an adequate and ascertainable description of the real estate to be charged) and that said work and labor was of the kind, was performed on the dates, for the purposes and at the prices, as shown in the following itemized account thereof:

(Here insert itemized account.)

You are further notified that the undersigned has not been paid the sum of $_____ (or that there is still due and owing to the undersigned thereon the sum of $ _____) and that he claims a lien upon your interest in the said lot (or tract) of land and upon the buildings, structures and improvements thereon to secure the payment of the said sum.

___________________

State of West Virginia,

County of___________

___________________, being first duly sworn, upon his oath says that the statements in the foregoing notice of mechanic’s lien contained are true, as he verily believes.

Taken, subscribed and sworn to before me this ______ day of ____, 20__

My commission expires __________________

___________________

(Official Capacity)

But the lien shall be discharged, unless such workman, artisan, mechanic, laborer or other person shall cause to be recorded in the office of the clerk of the county commission wherein such property is situate, within one hundred (100) days after he or she shall have ceased to do work or perform labor upon the building or improvement thereto, a notice of the lien, which notice shall be sufficient if in form and effect as that provided in section eight [s 38-2-8] of this article and which recorded notice need not include such itemized account.

38-2-14 Discharge of Lien, Failure to Give Notice

The failure of any person claiming a lien under this article to give such notice as is required by sections nine, eleven and thirteen [ss 38-2-9, 38-2-11, 38-2-13] of this article, or to record such notice as is required by sections eight, nine, ten, eleven, twelve and thirteen [ss 38-2-8 to 38-2-13] of this article, in the manner and within the time specified in such sections, or the failure of any such claimant of any such lien to comply substantially with all of the requirements of this article for the perfecting and preservation of such lien, within the time provided therefore in this article, shall, except as provided in section twenty [s 38-2-20] of this article, operate as a complete discharge of such owner and of such property from all liens for claims and charges of any such contractor, subcontractor, materialman or laborer, for any work claimed to have been performed and for any materials, machinery or other necessary equipment claimed to have been furnished in connection with such work.

38-2-15 Service by Publication

In the event that any owner, upon whose real estate or improvement thereof it is desired to take a lien under this article, should be a nonresident of this State, or in the event that any officer of this State authorized by law to execute legal process should make return not found upon any notice of a mechanic’s lien which may be presented to him for service, then it shall be sufficient service of any such notice of mechanic’s lien upon such nonresident owner, or upon such owner as to whom any such return, of not found shall be made by any such officer, to publish a copy of such notice as a Class II legal advertisement in compliance with the provisions of article three [s 59-3-1 et seq.], chapter fifty-nine of this Code, and the publication area for such publication shall be the county wherein the real estate lies. A copy of such notice shall also be posted in a conspicuous place upon the property sought to be charged thereby, which publishing and posting shall be sufficient, if commenced within the period provided by this article for the filing of such notice. The costs of such publication may be added to the account for which the lien is claimed, and, if included in the amount mentioned in the recorded notice the lien shall cover such costs.

38-2-16 One Contract

For the purposes of this article, all materials furnished, all work done, and all services provided by anyone person, firm or corporation, upon any one building or the improvements appurtenant thereto, or upon the real property whereon the same stands, or to which it may have been removed, shall be deemed and considered one contract, whether or not all of such material was bought at one time, or under one general agreement or otherwise, and whether or not all of such work, labor or services provided, was contracted for at one time or otherwise.

38-2-17 Priorities

A lien authorized and created by this article shall, when perfected, attach as of the date such labor, material, machinery or other necessary equipment shall have begun to be furnished, and shall have priority over any other lien secured by a deed of trust or otherwise which is created subsequent to such date. Each lien authorized and created by this article shall be subordinate to any other lien created by a deed of trust or otherwise which is duly recorded or otherwise perfected to constitute constructive notice prior to the date labor, material, machinery or other necessary equipment giving rise to such lien shall have begun to be furnished, notwithstanding the fact that some other lien authorized and created by this article may have priority over such other lien created by deed of trust or otherwise which is so recorded or otherwise perfected.

38-2-18 Priority Among Lien Claimants

Of the persons acquiring liens by virtue of this article and solely for determining priorities as among such persons, laborers, artisans, mechanics, workmen and furnishers of material, machinery and other necessary equipment, shall have first liens, and the lien of such persons, when perfected and preserved as required by this article, shall take precedence over any lien taken or to be taken by the contractor or subcontractor indebted to them for labor, material, machinery or other equipment, to the extent of the amount of the lien of such contractor or subcontractor, and the lien of a subcontractor shall take precedence over any lien taken or to be taken by a contractor indebted to him upon his subcontract, to the extent of the amount of the lien of such contractor, and every assignment or transfer by any such head contractor of his contract with the owner or by any such subcontractor of his contract with the contractor, or any proceeding in attachment or otherwise against such head contractor or subcontractor, with the purpose of encumbering or subjecting his interest in such contract, shall be subject and subordinate to the liens of all such subcontractors, laborers, workmen, artisans, materialmen and furnishers of machinery and other necessary equipment who shall perfect their liens according to the provisions of this article. But all of such perfected liens of such laborers and workmen and of such materialmen and furnishers of machinery and of such contractors and subcontractors, respectively, shall be of equal dignity without priority among themselves, except as otherwise provided in this article.

38-2-19 Demand for Itemized Account

The owner may, at any time, by notice in writing, require such subcontractor, laborer, mechanic, workman or other person doing, or causing to be done, work or labor upon such building or other structure or improvement appurtenant thereto, or any such materialman or other person furnishing materials, machinery or other necessary equipment for such work, to file with such owner an itemized account of the work done or caused to be done by such laborer or other person, or of the materials or machinery or other equipment furnished by such materialman or other person for such work, which account shall show the dates upon which such work was done, or such materials were furnished, the price charged therefore, and the nature of such work or materials, and the neglect or failure of any such laborer, mechanic or other person furnishing materials, machinery or other necessary equipment for the doing of the same, so to file such itemized statement with such owner, within ten days after the receipt by him of such written notice so to do, shall release such owner from all responsibility and his property from all lien or charge for all labor done and for all materials furnished by the person so failing to file such required itemized statement, prior to the giving of such notice.

38-2-20 Notice to Owner

Any laborer or other person employed to do any work or furnish any materials or machinery for the erection, construction, alteration, repair or removal of any building or other structure, or any improvement appurtenant thereto, by another who may have contracted with the owner therefore may, before doing any work or furnishing any material or machinery, give the owner of such building or other structure or improvement thereto notice in writing that if he is not paid therefore by the person employing him, he will look to the owner for payment; and it shall not be necessary for the person who has given such notice in writing to file the account and notice with the owner within sixty days of the date of the doing of the last work or of the furnishing of the last of such materials or machinery, unless he is required by the owner in writing within such sixty days to do so, and his neglect or failure to file such notice and account within sixty days, unless so requiredto do so, shall in no way affect or impair his lien if it be otherwise perfected and preserved, as provided in this article.

38-2-21 Effect of Payments by Owner

No payment by the owner to any contractor or subcontractor of any part or all of the contract price for the erection and construction of any such building, structure or improvement appurtenant thereto or for any part or section of such work shall affect, impair or limit the lien of the subcontractor, laborer, or materialman or furnisher of machinery or other necessary material or equipment, as provided for in this article, except as otherwise provided in this article.

38-2-22 Contracts to be Recorded with Bond, Effect

Any owner may limit his liability upon a contract such as is mentioned in section one [s 38-2-1] of this article, to the sum agreed therein to be paid therefore, by recording his contract with such general contractor, in the office of the clerk of the county court [county commission] of the county wherein such building or other structure is situate, prior to the beginning of the building, erection and construction thereof, and by requiring to be given by his general contractor, and by recording with such general contract, a valid and solvent bond, in a penalty equal to the contract price, with solvent surety, conditioned that in the event any laborer, materialman or other person, having perfected his lien as allowed by this article, be deprived by the recordation of the owner’s contract from receiving from such owner the amount of his lien, then such bond and the surety thereon shall be responsible to such lienor for the amount of such lien account, or for any balance thereof not collected by such lienor from such owner and from such property. Any such owner who shall cause his general contract to be recorded in such clerk’s office and who shall cause to be executed and recorded the bond therewith as hereinbefore provided shall be exempt from the payment of more than such contract price, and his property shall likewise be exempt therefrom, and all such liens created by this article as are not fully satisfied and discharged by such owner, by reason of such recordation, shall be paid by such contractor and his surety on such bond. If liens in excess of the contract price are perfected as provided in this article, the owner shall be liable to each lien claimant pro rata, in the proportion which the contract price bears to the total amount of the liens so perfected.

38-2-23 Failure to Record Contract and Bond, Effect

In the event any such owner should fail to record such contract and bond, or in the event the penalty of such bond should not be equal to the contract price, or in the event such bond should not be solvent at the time when given, then such contractor shall be deemed to be the agent of such owner and the building or other structure and the improvements appurtenant thereto, together with the interest of the owner thereof in and to the lot of land whereon the same stands or to which it is removed, shall be held liable and subject to such perfected liens, for the full and true value of all work and labor done and of all materials, machinery and equipment furnished therefore, although the same may exceed in the aggregate the price stipulated in the contract between the owner and the contractor.

38-2-24 Bond Form

The bond referred to in section twenty-two [s 38-2-22] of this article shall be sufficient if in form and effect as follows:

Know all men by these presents: That ___________ as principal, and _____________ as sureties (or surety) are held and firmly bound unto ___________ in the just and full sum of $________, to the payment whereof well and truly to be made, we bind ourselves, our heirs, administrators and assigns, jointly and severally by these presents.

Sealed with or seals and dated this ______ day of _____, 20

The condition of the above obligation is such: That whereas, the said ___________ has entered into a certain contract with ___________ for the building and erection by the said ____________ for the said ___________ of a certain ___________, to be situated ___________; and whereas, it is agreed between the above named principal and surety that no change or modification of such contract shall operate to discharge the surety upon this bond; now, therefore, if the said ___________ shall well and truly perform his said contract, and shall pay off, satisfy and discharge all claims of subcontractors, laborers, materialmen and all persons furnishing material or doing work upon said building and shall save the said ____________ and his property harmless from any and all liability, over and above the contract price thereof, between the said owner and the said contractor, for all of such labor and materials, and shall fully pay off and discharge and secure the release of any and all mechanics’ liens which may be placed upon said property by any such subcontractor, laborer or materialman, then this obligation shall be null and void. Otherwise it shall remain in full effect.

____________(Seal)

____________(Seal)

____________(Seal)

Acknowledged before the subscriber, a notary public, in and for the State of West Virginia and County of _________, this ______ day of _______, 20__

My commission expires _________

____________________Notary Public.

No change or modification of any such contract between such owner and such general contractor shall operate to discharge or release the obligation of the surety or sureties upon any such bond.

38-2-25 Property Outside City

Whenever a lien, perfected and preserved under this article is sought to be enforced against any property outside of any city, town or village, it shall be the duty of the court before which any suit for the enforcement of such lien is pending, to determine in its discretion how much land surrounding any such building shall be subject to such lien. In any event, not more of such land shall be so subject to such lien than shall be reasonably necessary to the full enjoyment of such building or other improvement.

38-2-26 Parties

Whenever it shall be necessary for suit to be brought as hereinafter provided, for the enforcement of any of the liens contemplated by this article, such contractor and the sureties upon such bond mentioned in sections twenty-two, twenty-three and twenty-four [ss 38-2-22 to 38-2-24] of this article, shall be made parties thereto and all matters arising upon such bond and the liabilities thereunder shall be litigated and determined in such suit to enforce the lien and it shall not be necessary for judgment upon such bond to be taken at law, but all such proceedings as are necessary to enforce liability upon such bond shall be had in such court of chancery, according to the usual and ordinary course of proceeding therein.

38-2-27 Recordings

It shall be the duty of the clerk of the county court [county commission] of the county to enter every notice of lien mentioned in this article upon the filing in his office of such notice in a book by him to be kept for that purpose, to be called Mechanic’s Lien Record, which book shall be well and properly indexed, so as to show the names of the parties, the amount and character of the claim, when filed, and the description of the property to be charged by such lien. The contract and bond mentioned in section twenty-two [s 38-2-22] of this article shall also, when filed in the office of such clerk, be entered in the mechanic’s lien record and indexed.

38-2-28 Proof of Sale, Effect

Proof of the sale to any owner, contractor or subcontractor of any materials, machinery or other equipment for use in the performance of any contract mentioned in this article, and of the delivery of such materials, machinery or other equipment to such contractor or subcontractor, shall be prima facie proof of the use of such materials, machinery or equipment in the erection and construction of such building or other structure and of the improvements appurtenant thereto, and upon the proving of such facts, the burden of showing that such materials, machinery and equipment were not used in such building or other structure or improvement appurtenant thereto shall be upon the owner or other person disputing such use thereof.

38-2-29 Multiple Improvements

Any materialman or furnisher of machinery or other equipment necessary to the performance of any one such general or subcontract, who shall furnish such materials, machinery or other equipment in quantities for use in more than one building or other structure or improvement appurtenant thereto, and any workman, laborer or other person who shall perform work or labor upon more than one such building or other structure or improvement appurtenant thereto, provided for in such contract, shall have a lien upon all of such buildings and other structures and improvements into which his materials were put or upon which his work and labor was expended and upon the interest of the owner in and to the lot of ground upon which all of such buildings and structures stand or

38-2-30 Prevention of Performance

When the owner fails to perform his part of the contract and by reason thereof the other party, without his own default, is prevented from completely performing his part, he shall be entitled to reasonable compensation for so much as he shall have performed, in proportion to the price stipulated for the whole, and shall have such a lien as is provided in this article, to secure payment thereof, when such lien is properly perfected and preserved according to the provisions of this article.

38-2-31 Lien of Worker Against Property of Corporation, Limitations

Every workman, laborer or other person who shall do or perform any work or labor, for an incorporated company doing business in this State, by virtue of a contract either directly with such incorporated company or with its general contractor, or with any subcontractor, shall have a lien for the value of such work or labor upon all real estate and personal property of such company; and, to the extent and value of one month’s such work or labor, said lien shall have priority over any lien created by deed or otherwise on such real estate or personal property subsequent to the time when such work or labor was performed: Provided, however, that there shall be no priority of lien as against conditional sales of, or reservation of title to, machinery sold to such company; nor shall there be priority of lien as between the parties claiming under the provisions of this section.

38-2-32 Discharge of Lien Against Corporation, Notice of Lien

Such lien shall be discharged unless the person desiring to avail himself thereof, within one hundred (100) days from the time he shall have ceased to work or labor for such incorporated company or for such contractor, shall file with the clerk of the county court [county commission] of the county in which such work or labor was performed, or in which the principal office, works, real estate or personal property of such incorporated company is situated, a notice of lien containing the amount due him after allowing all credits, which notice shall be sworn to by the person claiming such lien, or by someone in his behalf.

38-2-33 Recording

The clerk of the county court [county commission], to whom the notice of lien mentioned in the preceding section [s 38-2-32] is presented, shall record the same in the mechanic’s lien record. If the amount of the claim is for more than one month’s work or labor, the record shall show, separately, the full amount of the claim and in addition thereto the amount of the claim for such month for which such prior lien is claimed.

38-2-34 Actions, Limitations, Intervention

Unless a suit in chancery to enforce any lien authorized by this article is commenced within six months after the person desiring to avail himself thereof shall have filed his notice in the clerk’s office, as hereinbefore provided in this article, such lien shall be discharged; but a suit commenced by any person having such lien shall, for the purpose of preserving the same, inure to the benefit of all other persons having a lien under this article on the same property, and such persons may intervene in such suit for the purpose of enforcing their liens, in the same manner as in other chancery suits.

38-2-35 Sale, Personal Judgment

If the lien or liens be established in favor of any of the creditors whose claims are presented in the suit mentioned in the preceding section [s 38-2-34], the court shall order a sale of the property on which the liens are established, or so much thereof as may be sufficient to satisfy such claims, in like manner as in other suits in chancery, and the court may, in addition, give a personal decree in favor of such creditors for the amount of their claims against any party against whom they may be established, and such decree shall have the effect of, and be enforced as, other decrees for money.

38-2-36 Discharge of Lien, Deposit in Court, Hearing, Release, Escrow, Action, Receiver

(a) When a debt secured by any lien mentioned in this article is fully paid at any time after the lien creditor shall have filed his notice of such lien in the office of the clerk of the county commission, such creditor assignee shall cause the clerk to enter a discharge of such lien in the margin of the book in which such account is entered and immediately opposite thereto, or shall execute a release thereof, which shall be recorded in the book in which such notice is entered and noted on the margin of such notice.

(b)(1) At any time after a lien creditor has given notice of lien as required by the provisions of this article and has subsequently duly filed such notice of lien with the clerk of the county commission as provided for in this article, the owner or any person against whom the lien is claimed may apply to the circuit court having jurisdiction to enforce such lien, by petition, for an order authorizing such owner or other person against whom the lien is claimed to deposit, in escrow, with the clerk of the circuit court, an amount equal to the sum set out as due in the notice of lien, and directing the circuit clerk to execute a release of the lien. Previous to the filing of such petition, the petitioner shall cause to be served upon the lien creditor a notice of the time and place that such application will be made, which notice shall be served by registered mail, return receipt requested, addressed to the lien creditor or his authorized agent at the address set forth in the notice of lien: Provided, that if no such address is set forth in the notice of lien, the petitioner shall serve the notice, setting forth the time and place that his application will be made, in the same manner as original process is served for the commencement of civil actions.

(2) At the hearing upon the petition, the court shall ascertain what interest, if any, might reasonably be expected to accrue on the sum claimed to be due, either by contract or by operation of law, and subsequently be payable to the lien creditor, should he prevail upon his claim. The court shall also determine the current rate of return upon investments made by the general receiver of the court at the time of the hearing, and ascertain what rate of interest might reasonably be earned upon the petitioner’s escrow deposit when paid into the court. To the extent that the anticipated interest due to the lien creditor exceeds the anticipated return upon the investment of the escrow deposit, the court may require an additional deposit beyond the sum set forth in the notice of lien, as the interests of the parties may require. The order authorizing the deposit and directing the execution of the release shall, if the court anticipates that complex or extended litigation may arise in resolving the issue of the validity of liens or claims in the case, require that the petitioner or other parties give security before the court, or the clerk thereof, for payment of the costs which may be awarded in the court, and of the fees due, or to become due, in any action to determine such issue.

(3) If an escrow deposit is authorized by the court, such deposit shall be made by cash, and when paid into court, shall be received by the general receiver of the court, who shall take charge of and invest the money deposited in the manner provided for in section one [s 51-6-1], article six, chapter fifty-one of this Code until otherwise ordered to pay out or dispose of the same by the circuit court. Upon presentation to the clerk of the county commission wherein the notice of lien is filed of an order of the court and a receipt executed by the clerk of the circuit court for the amount required to be deposited by the terms of the order, the clerk of the county commission shah file the order and shall enter a discharge of the lien in the margin of the book in which such account is entered and immediately opposite thereto, or shall execute a release thereof, which shall be recorded in the book in which such notice is entered and noted on the margin of such notice.

(4) Unless an action to determine the validity of the creditor’s claim is commenced within six months after the creditor shall have filed his notice of lien in the office of the clerk of the county commission as provided for in this article, the court shall, upon motion of the depositor, order the general receiver to pay out to the depositor the sum deposited, together with any dividends and interest, if any, earned upon the investment of the deposit, less any compensation for the services of the general receiver as the court may direct in accordance with the provisions of section seven [s 51-6-7], article six, chapter fifty-one of this Code. If the claim is satisfied or settled and compromised at any time while secured by the deposit made with the general receiver but before an action is commenced, the court shall, upon proof of satisfaction or settlement and compromise, order the general receiver to payout the deposit to the depositor in the same manner as though suit was not commenced within the requisite period of six months as described above. If an action is commenced, the general receiver shall thereafter pay out the money deposited and the dividends and interest, if any, earned upon the investment of the deposit, as the court may order or decree, less any compensation for the services of the general receiver as the court may direct in accordance with the provisions of said section seven [s 51-6-7].

38-2-37 Order of Discharge, Costs

In case of the refusal of the party holding such lien to cause such clerk to enter a discharge of such lien, or to execute a release of such lien, in the manner provided in the preceding section [s 38-2-36] of this article, upon the request of the party entitled to such discharge or release, the circuit court of the county, or the judge thereof in vacation, in which such lien is recorded may, on motion, after reasonable notice of the party so refusing, and if no good cause be shown against it, direct the clerk of the county court [county commission] to enter such discharge, which shall thereupon have the effect of a discharge entered under the provisions of the preceding section. Such proceeding shall be at the cost of the party so refusing.

38-2-38 Executor, Administrator, Assignee

The executor or administrator of any person entitled to a lien under this article, or any assignee of the claim upon which such lien is based, shall be entitled to such lien, and to the right to perfect and enforce such lien, in the same manner and to the same extent as the testator, intestate, or assignor could have done, had he remained the owner of such claim.

38-2-39 Public Projects, Payment Bond, No Lien

It shall be the duty of the State commissioner of public institutions[department of corrections],and of all county courts [county commissions],
boards of education, boards of trustees, and other legal bodies having authority to contract for the erection, construction, improvement, alteration or repair of any public building or other structure, or any building or other structure used or to be used for public purposes, to require of every person to whom it shall award, and with whom it shall enter into, any contract for the erection, construction, improvement,
alteration or repair of any such public building or other structure used or to be used for public purposes, that such contractor shall cause to be executed and delivered to the secretary of such commissioner or other legal body, or other proper and designated custodian of the papers and records thereof, a good, valid, solvent and sufficient bond, in a penal sum equal at the least to the reasonable cost of the materials, machinery, equipment and labor required for the completion of such contract, and conditioned that in the event such contractor shall fail to pay in full for all such materials, machinery, equipment and labor delivered to him for use in the erection, construction, improvement, alteration or repair of such public building or other structure, or building or other structure used or to be used for public purposes, then such bond and the sureties thereon shall be responsible to such materialman, furnisher of machinery or equipment, and furnisher or performer of such labor, or their assigns, for the full payment of the full value thereof. All such bonds shall have as surety thereon either some incorporated bonding and/or surety company authorized to carry on business in this State, or in lieu of such corporate surety the contractor may deposit as security for such bond with the said State commissioner of public institutions [department of corrections], county court [county commission], board of education, board of trustees or other legal body having authority so to contract, a sum in cash or bonds and securities of the United States of America or of the State of West Virginia of sufficient amount and value equal at least to the reasonable cost of materials, machinery, equipment and labor required for the completion of such contract. Immediately upon the acceptance of either of said bonds by the State commissioner of public institutions [department of corrections], county court [county commission], board of education and board of trustees, or other legal body, the bond shall be recorded by the secretary of such commissioner [department] or other legal body, or by the proper designated custodian of the papers or records thereof, in the office of the clerk of the county court [county commission] of the county or counties wherein such work is to be done and where such materials, machinery or equipment are to be delivered, and no such contract shall be binding and effective upon either party or parties thereto until such bond has been executed, delivered and recorded as aforesaid. Nothing in this article shall be construed to give a lien upon such a public building or improvement as is mentioned in this section, or upon the land upon which such public building or improvement is situated.

ARTICLE 12 RELEASE AND ASSIGNMENT OF LIENS

38-12-1 Satisfaction, Release

(a) Every person entitled to the benefit of any lien on any estate, real or personal, or to the money secured thereby, whether the lien was created by conveyance, judgment, decree, lis pendens, notice of attachment, deed of trust, contract or otherwise, shall be required to furnish and execute an apt and proper written release thereof free of charge to the debtor whose obligation secured by such lien has been fully paid and satisfied, if the lien is of record in the proper county. Such release shall be executed and furnished to the debtor within thirty days after the debt has been satisfied.

(b) Such release of lien shall be executed by the lienholder and acknowledged before the clerk of the county commission in whose office the lien is recorded or before such other person authorized to take acknowledgments of deeds. Such written release shall be deemed sufficient if it describe the lien to be released by any words that will identify and show an intent to discharge the same. Releases may also be made according to the provisions of section two [s 38-12-2] of this article.

38-12-2 Release by Trustee

A trustee in a trust deed may release the lien of such trust deed:

(a) When the trust deed authorizes the trustee to release the same;

(b) When the trust deed creates a lien to secure debts to persons not named in the trust deed;

(c) When a trust deed creates a lien to secure more than five creditors, even though such creditors be named in the trust deed;

(d) When a trust deed creates a lien to secure notes or bonds or other instruments payable to bearer.

A release executed by the trustee in any of the cases mentioned herein, and properly recorded, shall, as to purchasers for value without notice, be valid and binding, whether the debt secured by such lien had in fact been paid or discharged or not.

38-12-3 Release by Trustee, Publication of Notice

If a trustee in a trust deed which secures persons not named in the trust deed shall publish, as hereinafter provided, a notice that he will, on a day named in such notice, such day to be not more than thirty nor less than ten days after the last publication of such notice, release such trust deed, such trustee may execute such release and make distribution of any funds in his hands as such trustee without any liability to any person not named in the trust deed nor known to the trustee to be a beneficiary of the trust. Such notice shall be published as a Class II legal advertisement in compliance with the provisions of article three [s 59-3-1 et seq.], chapter fifty-nine of this Code, and the publication area for such publication shall be the county in which such trust deed is recorded.

38-12-4 Form of Release

Releases and their acknowledgments may be substantially in form or effect as follows:

(a) In case of a mortgage or trust deed: I, A. ___ ___ B. ___, hereby release a mortgage (or trust deed) made by C. ___ ___ D. ___ to me (or to E. ____ F. ____, my trustee, or to ____, and assigned to me) dated the ____ day of ____, recorded in the office of the clerk of the county court [county commission] of _____ county, West Virginia, in trust deed book ____, page ____(Or, in case the release is by the trustee, I, A. ____.

B. ____, hereby release a trust deed made by C. ____ D. ____ to me as trustee, for the benefit of E. _____ F. ____, dated the ____ day of ____, recorded, etc., as in preceding form.)

To be signed A. ____ B. _____

Acknowledged before the subscriber, by A. ____ B. ____, this ____ day of ____ (or, in case the release be by a corporation, acknowledged before the subscriber, by ____, who signed the name of ____, a corporation, thereto, this ____ day of ____, _____)

(To be signed) G. ____ H. ______, a justice (or clerk of the county court [county commission], notary public, etc., as the case may be) of _____ county, West Virginia.

(b) In case of a lien for purchase money, reserved by conveyance: I, A. ___ B. ___, hereby release the right reserved to me in a conveyance executed by me (or myself and wife) to C. ___ ___ dated the ___ day of ___ (Or, in case of an assignment, I, A. ___ B. ___ hereby release the right reserved by C. ___ D. ___ in a conveyance to E. ___ F. ___, dated the ___ day of ___ ., ___, which right was assigned by the said C. ___ D. ___ to me, the ___. day of ___, ___) To be signed and acknowledged as above.

(c) In case of a judgment or decree: I, A. ___ B. ___ ___, hereby release a judgment (or decree) in my favor (or in favor of I. ___ K. ___, which has been assigned to me, or in favor of I. ___ K. ___ for my use) against C. ___ D. ___, for (stating the amount) with interest and costs, rendered by (stating the court by which, or the justice [magistrate] by whom, it was rendered, and the term or date at which it was rendered, to be signed and acknowledged as above.) When such lien is release by the assignee thereof, the assignment thereof, whether of the lien or of the debt secured thereby, must be acknowledged in the same manner as the release, and recorded with such release: Provided, that if any such lien, or the debt secured thereby, shall have been assigned, the same may always be released by the assignee who receives satisfaction thereof, upon the assignor joining therein, without the recordation of the assignment as aforesaid.

38-12-5 Partial Release

In case of a discharge of only a part of the lien debt, or a release of only a part of the property subject to the lien, or any other partial or limited release, the form of release prescribed in section four [s 38-12-4] of this article may be modified to express the facts and the intention of the parties.

38-12-6 Release by Assignor, Liability

Any person who shall have been entitled to the benefit of any lien and who shall have assigned such lien, or the benefit thereof, or any instrument secured by such lien, to any other person, shall be liable to any person injured by any release executed by such person first mentioned, after such assignment.

38-12-7 Personal Representative

In case of the death, insanity, or infancy of the person entitled to the lien, the release may be made by the personal representative, committee, or guardian of such person, as the case may be.

38-12-8 Recording

When the release has been so signed and acknowledged, it may be presented for record to the clerk in whose office the lien thereby intended to be released is recorded or docketed, and from and after the time the same is so left for record (which time the clerk shall indorse thereon) such lien shall be discharged and extinguished, and the estate, of whatever kind, bound or affected thereby, shall be deemed to be vested in the former owner or those claiming under him, as if such lien had never existed.

38-12-9 Recording, Indexing

The clerk of the county court [county commission] shall record and properly index all releases and assignments admitted to record in his office under the provisions of this article, in a well-bound book to be kept exclusively for the purpose, and, when any such instrument is recorded, he shall note the fact on the margin of the record or docket of the lien affected or discharged thereby, with a reference to the book and page where such release or assignment is recorded.

38-12-10 Action for Failure to Release

In case of the failure of the party holding such lien to furnish and execute an apt and proper release upon request of the party entitled thereto as required by section one [s 38-12-1] of this article, the circuit court having jurisdiction may, on motion, after reasonable notice to the party so failing, and if no good cause be shown against it, direct the clerk of the county commission to execute such release, and it shall thereupon have the effect of releases executed under section one of this article. The proceedings shall be at the cost of the lienholder who so refuses without good cause and the court shall also award reasonable attorney fees and court costs to the person entitled to such release if such person be the prevailing party.

38-12-11 Discharge or Impairment

Nothing in this article contained shall be construed to authorize the discharge of any lien contrary to the provisions of the instrument under which the lienor claims, or to impair or affect the validity of any deed of release, or other writing discharging any lien in this article mentioned, either heretofore or hereafter created or made.

38-12-12 Satisfaction, Entry

When an execution issued upon a judgment or decree, which has been entered in the judgment lien docket in the office of the clerk of the county court [county commission], is returned satisfied, the clerk, to whose office such return is made, shall certify the same to the clerk of the county court [county commission], and such return shall be entered by such clerk in the margin of the docket of such judgment or decree.

38-12-13 Liability of Clerk

If any clerk or other officer shall fail in any duty imposed upon him by this article, he shall be liable to any party injured for all damages caused by such failure, or the person injured may, at his option, recover the sum of fifty dollars from