On private Commercial projects NORTH CAROLINA General Statutes § 44A-23mandate that in order for Subcontractors to protect their lien rights, they need to deliver by certified mail or personal delivery to the General/Prime Contractor and other legal parties (Customer, Lender/Surety, Owner) a Notice Of Subcontract when the General/
Prime Contractor files a NORTH CAROLINA Notice Of Contract. NORTH CAROLINA law does not require the Prime/General Contractor to always file a Notice Of Contract.
NORTH CAROLINA General Statutes § 44A-23 mandate that a General/Prime contractor can record a NORTH CAROLINA Notice Of Contract within thirty (30) days of a building permit being issued. It is recorded at the Offfice Of The Clerk Of The Superior Court where the property to be improved is located. A Notice Of Contract protects General/Prime contrators from liens filed by second and third tier subcontractors who fail to deliver a NORTH CAROLINA Notice Of Subcontract.
TRADITION LIEN SERVICE can research and send this notice on your behalf for only $24. Or, you can print this NORTH CAROLINA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.
|
On private Existing Residential projects NORTH CAROLINA General Statutes § 44A-23mandate that in order for Subcontractors to protect their lien rights, they need to deliver by certified mail or personal delivery to the General/Prime Contractor and other legal parties (Customer, Lender/Surety, Owner) a Notice Of Subcontract when the General/
Prime Contractor files a NORTH CAROLINA Notice Of Contract. NORTH CAROLINA law does not require the Prime/General Contractor to always file a Notice Of Contract.
NORTH CAROLINA General Statutes § 44A-23 mandate that a General/Prime contractor can record a NORTH CAROLINA Notice Of Contract within thirty (30) days of a building permit being issued. It is recorded at the Offfice Of The Clerk Of The Superior Court where the property to be improved is located. A Notice Of Contract protects General/Prime contrators from liens filed by second and third tier subcontractors who fail to deliver a NORTH CAROLINA Notice Of Subcontract.
TRADITION LIEN SERVICE can research and send this notice on your behalf for only $24. Or, you can print this NORTH CAROLINA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.
|
On private New Residential projects NORTH CAROLINA General Statutes § 44A-23mandate that in order for Subcontractors to protect their lien rights, they need to deliver by certified mail or personal delivery to the General/Prime Contractor and other legal parties (Customer, Lender/Surety, Owner) a Notice Of Subcontract when the General/
Prime Contractor files a NORTH CAROLINA Notice Of Contract. NORTH CAROLINA law does not require the Prime/General Contractor to always file a Notice Of Contract.
NORTH CAROLINA General Statutes § 44A-23mandate that a General/Prime contractor can record a NORTH CAROLINA Notice Of Contract within thirty (30) days of a building permit being issued. It is recorded at the Offfice Of The Clerk Of The Superior Court where the property to be improved is located. A Notice Of Contract protects General/Prime contrators from liens filed by second and third tier subcontractors who fail to deliver a NORTH CAROLINA Notice Of Subcontract.
TRADITION LIEN SERVICE can research and send this notice on your behalf for only $24. Or, you can print this NORTH CAROLINA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.
|
Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Claim Of Lien On Real Property or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.
TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $45. Or, you can print this NORTH CAROLINA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.
|
Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Claim Of Lien On Real Property or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.
TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $45. Or, you can print this NORTH CAROLINA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.
|
Optional. Consider delivering by certified mail a Notice Of Intent To File A Bond Claim, Claim Of Lien On Real Property or Stop Notice to the Owner and other legal parties ten (10) days before recording a lien.
TRADITION LIEN SERVICE can research and and send this notice on your behalf for only $45. Or, you can print this NORTH CAROLINA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.
|
On private Commercial projects NORTH CAROLINA General Statutes § 44A-7 mandate that General/Prime Contractor record a NORTH CAOLINA Claim Of Lien On Real Property within one hundred twenty (120) days of last providing labor or materials for a project. It must be filed with the Clerk of the Superior Court in the county where the project is located. The Claim Of Lien On Real Property must then be enforced through a lawsuit within one hundred eighty (180) days of last providing labor or material for a project.
NORTH CAROLINA General Statutes §§ 44A-20(d), 44A-23 mandates that Subcontractors can record a Claim Of Lien On Real Property up to one hundred twenty (120) days after the last day providing equipment, labor, materials or sevices for a project. Deliver at same time by certifed mail or personal delivery to the Owner and other legal parties a NORTH CAROLINA Notice Of Claim Of Lien Upon Funds By First, Second Or Third Tier Subcontractor/ Supplier. It does not need to be filed with the Clerk of the Superior Court in the county where the project is located. There is no time limit to enforce through a lawsuit a NORTH CAROLINA Notice Of Claim of Lien Upon Funds By First, Second Or Third Tier Subcontractor/
Supplier. The Owner or party oweing the money for the project has an obligation to withhold payment to the General/Prime Contractor until the lien claimant’s payment is satisfied.
TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $165. Or, you can print this NORTH CAROLINA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.
|
On private Existing Residential projects NORTH CAROLINA General Statutes § 44A-7 mandate that General/Prime Contractor record a NORTH CAROLINA Claim Of Lien On Real Property within one hundred twenty (120) days of last providing labor or materials for a project. It must be filed with the Clerk of the Superior Court in the county where the project is located. The Claim Of Lien On Real Property must then be enforced through a lawsuit within one hundred eighty (180) days of last providing labor or material for a project.
NORTH CAROLINA General Statutes §§ 44A-20(d), 44A-23 mandates that Subcontractors can record a Claim Of Lien On Real Property up to one hundred twenty (120) days after the last day providing equipment, labor, materials or sevices for a project. Deliver at same time by certifed mail or personal delivery to the Owner and other legal parties a NORTH CAROLINA Notice Of Claim Of Lien Upon Funds By First, Second Or Third Tier Subcontractor/
Supplier. It does not need to be filed with the Clerk of the Superior Court in the county where the project is located. There is no time limit to enforce through a lawsuit a NORTH CAROLINA Notice Of Claim of Lien Upon Funds By First, Second Or Third Tier Subcontractor/
Supplier. The Owner or party oweing the money for the project has an obligation to withhold payment to the General/Prime Contractor until the lien claimant’s payment is satisfied.
TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $165. Or, you can print this NORTH CAROLINA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.
|
On private New Residential projects NORTH CAROLINA General Statutes § 44A-7 mandate that General/Prime Contractor record a NORTH CAROLINA Claim Of Lien On Real Property within one hundred twenty (120) days of last providing labor or materials for a project. It must be filed with the Clerk of the Superior Court in the county where the project is located. The Claim Of Lien On Real Property must then be enforced through a lawsuit within one hundred eighty (180) days of last providing labor or material for a project.
NORTH CAROLINA General Statutes §§ 44A-20(d), 44A-23 mandates that Subcontractors can record a Claim Of Lien On Real Property up to one hundred twenty (120) days after the last day providing equipment, labor, materials or sevices for a project. Deliver at same time by certifed mail or personal delivery to the Owner and other legal parties a NORTH CAROLINA Notice Of Claim Of Lien Upon Funds By First, Second Or Third Tier Subcontractor/
Supplier. It does not need to be filed with the Clerk of the Superior Court in the county where the project is located. There is no time limit to enforce through a lawsuit a NORTH CAROLINA Notice Of Claim of Lien Upon Funds By First, Second Or Third Tier Subcontractor/
Supplier. The Owner or party oweing the money for the project has an obligation to withhold payment to the General/Prime Contractor until the lien claimant’s payment is satisfied.
TRADITION LIEN SERVICE can research, prepare and record this notice on your behalf for only $165. Or, you can print this NORTH CAROLINA notice and others by purchasing PreLien2Lien from TRADITION SOFTWARE for as little as $149.
|